Free inspection and test plan (ITP) template for construction

Every check a piece of work needs before it's covered up: the inspection, what a pass looks like, hold and witness points, and a signature against each one.

Published 5 min read

Inspection and test plan

PDF, 1 page, A4 landscape · Free · No email required

Signing off ITPs on several jobs? Foreman's forms let your site managers tick each check, add a photo at every hold point and sign it off on their phone. Free on your first job, with every feature and unlimited users on it.

One-page landscape inspection and test plan with columns for activity, inspection or test, acceptance criteria, reference, hold or witness point, responsible person and sign-off

An inspection and test plan (ITP) lists every check a piece of work needs before it's covered up or handed over: what gets inspected, what "pass" means, who checks it, and where work has to stop until it's signed off. This one-page landscape template has the columns head contractors and quality auditors expect, with two worked examples to start from.

Free, no email required.

What an ITP is for

An ITP is a quality record. It's written before the work starts, it travels with the job, and each row gets signed as the work is checked. When a head contractor, a client or an ISO 9001 auditor asks how you know the footings were right before the pour, the signed ITP is the answer.

It isn't a safety document. The SWMS covers how the work is done safely. The ITP covers whether the finished work is right.

What goes in each column

Activity. The piece of work, in the order it happens on site: excavation, reinforcement, the pour, framing, waterproofing.

Inspection or test. What you physically check. "Bar size, spacing, cover and laps" is a check. "Reo OK" isn't.

Acceptance criteria. What a pass looks like, in a form someone else could check: the drawing number, the standard, the tolerance.

Reference. Where the criteria come from, so anyone can find them: the engineer's drawing, the specification clause, the Australian Standard.

H, W or R. The column that matters most.

  • A hold point (H) means work stops until this is inspected and released. Reinforcement before a pour is the classic example, because you can't check it afterwards.
  • A witness point (W) means the client or their representative gets notice and can attend if they want to.
  • A record (R) just needs the check documented.

Responsible, checked by, date, pass. One name against each check, and a signature and date when it's done. An ITP with blank sign-offs proves the plan existed, not that anyone followed it.

What people get wrong

One generic ITP for every job. Write it for this job's drawings and this job's specification. The template gives you the structure, but the rows are yours.

Too many hold points. If everything is a hold point, the site stops every hour and people start ignoring them. Keep hold points for work you genuinely can't check later.

No photos. A tick in the pass column is good. A photo of the reinforcement before the pour, dated and against the job, is much better when the slab is questioned two years later.

Doing it without the clipboard

Foreman's forms suit an ITP well. Build it once with a checklist for each activity, a photo field for the evidence at each hold point, and a signature field for whoever releases it. You can lock the date to the day it's filled in, so the record shows when the check really happened, and limit the form to site managers and admins.

Already have your ITPs as PDFs? Connect Claude or ChatGPT to Foreman, give it the PDF, and ask it to build the form.

The same day's site diary entry holds the wider record: who was on site, the hours and any other photos.

The daily pre-start checklist covers safety checks before work each morning. The defect list template is for what's left at handover, and what a SWMS is covers the safety side of high risk work.

Frequently asked questions

What is an ITP in construction?
An inspection and test plan lists every check a piece of work needs: what is inspected, the acceptance criteria, where the criteria come from, who checks it, and the hold and witness points. Each row is signed as the work is checked, so the ITP becomes the quality record for that work.
What is a hold point?
A point where work must stop until an inspection is done and the work is released, usually because it can't be checked later. Reinforcement before a concrete pour is the classic example.
What is the difference between a hold point and a witness point?
At a hold point, work stops until the check is signed off. At a witness point, the client or their representative is given notice and may attend, but work can continue if they don't.
Is an ITP the same as a SWMS?
No. A SWMS sets out how high risk work will be done safely. An ITP sets out how you'll check the finished work is right. Many jobs need both.

Keep your sites in order

Every hold point signed off, with a photo.

Build your ITP once as a Foreman form, with a checklist, photos and signatures. Site managers sign off each check on their phone, saved against the job. Free on your first job.