How to show workers your pre-start or toolbox talk at induction
Put today's hazards in front of everyone who comes through the gate, with a signed record that they saw them.
To have workers read your pre-start or toolbox talk as part of their induction, upload it as a PDF to the site's induction documents. It then shows on the induction page above the Declaration, so everyone who scans the gate QR code opens it before they sign. Their signature and the time go into the site's induction register, next to the documents they were shown.
It's a simple way to prove that everyone coming through the gate saw the day's hazards, which is what ISO 45001 auditors and head contractors look for.
An Admin can set this up on any project. A Site Manager can do it on the projects they manage.
Add the pre-start or toolbox talk to the induction
- Save the pre-start or toolbox talk as a PDF. A photo of a paper sheet works too, as a JPG or PNG.
- Open the project and tap Edit.
- Under Induction, find Extra documents for this site and tap Upload.
- Pick the file. Put it in a folder such as "Pre-start" or "Toolbox talks" if you like, then confirm the upload.
- Tap Preview under the induction to check it as a visitor will see it.
Name the file so people know what it is at a glance, like "Toolbox talk - Working at heights - week 46". The name is what they see in the list.
Make reading it part of what they sign
The standard Declaration already covers reviewing the site's safety documents. To make it explicit, an Admin can add a numbered point to the template's declaration, such as "6. I have read today's pre-start and the current toolbox talk for this site." Every person who signs agrees to it, and the wording is saved with their record. See how to set up a site induction.
Keep it current
A pre-start changes every day and a toolbox talk usually every week. Swap the file rather than adding a new one each time, so nobody reads last week's version:
- Open the project and tap Edit.
- Under Induction, open the document's actions menu and choose Replace file.
- Pick the new PDF. It takes the old one's place under the same name, so rename it if the date is in the title.
Every past induction record still shows the documents that person was shown when they signed.
Your own crew
Visitors and subbies sign the induction every time they come through the gate, so they'll see today's file. Your crew with logins work differently. Depending on how your business records hours, they sign each site's induction once or not at all. See what workers see when they scan.
For a daily record from your crew, run the pre-start as a Foreman form instead:
- The site manager fills in the pre-start on their phone each morning: checks, hazards, controls and a signature, saved with the time it was sent. See how to run a daily pre-start.
- Each crew member signs on with a short "Pre-start sign-on" or "Toolbox talk sign-on" form after the talk: a locked Date and a Signature. See how to build a form template.
Together, that gives you the pre-start itself, a signature from every crew member who was there, and an induction record for every subbie and visitor who saw it at the gate.
Good to know
- Induction documents are public on purpose. Anyone with the site's induction link can open them, so keep anything private in the project's Documents instead. See project information and documents.
- One toolbox talk for every site? Put it in the induction template's Documents block instead, and every project on that template shows it.
- The register records the signature and the time. It doesn't track whether someone opened each file, which is why the declaration point above is worth adding.