Free hot work permit template for construction
Location and time window, ten fire precautions to check before the first spark, a named fire watch, both signatures, and a close-out after the fire watch. With a filled-in example.
Hot work permit
PDF, 1 page, A4 · Free · No email required
Issuing permits on several jobs? Foreman's forms let you build this permit once as a form. The supervisor ticks the precautions and both people sign on the phone at the work, with the date locked to today. Start free on your first job

A hot work permit is the sign-off a supervisor gives before anyone welds, cuts, grinds, brazes or solders where sparks or heat could start a fire. This one-page permit covers the location and time, the work, ten precautions to check before the first spark, both signatures, and a close-out once the fire watch is done.
Free, no email required.
When you need a hot work permit
Any time hot work happens near something that could burn: timber framing, insulation, sarking, packaging, a ceiling cavity, fuel or gas. On a building site that's most of the time. A permit isn't needed for a welding bay set up for the purpose, away from combustibles. It is needed for the plumber silver-soldering a pipe inside a timber-framed wall.
No WHS regulation calls it a "hot work permit" by name. The duty is the general one to identify hazards and eliminate or minimise the risk (regs 34 to 38 of the model WHS Regulations), here the risk of fire. The permit is how most sites show they did that. SafeWork NSW points to the Australian Standard for fire precautions in welding and cutting, AS 1674.1, which includes an example of a typical hot work permit, and your head contractor or insurer may require one, so check the contract and the policy.
What goes on a hot work permit
Where, when and what. The exact location, not just the address, and the time window. One permit covers one location for one shift. If the work moves or runs into the next day, issue a new one.
Who. The person doing the work, and a named fire watch. The fire watch is a real job: they stay with the work, keep an eye on the sparks, and have an extinguisher in their hand, not in the ute.
Precautions. Ten checks before work starts. Combustibles moved or covered. No flammable liquids or vapours nearby. An extinguisher or charged hose at the work. Sparks contained. Gas cylinders secured with flashback arrestors. The areas above, below and behind checked, which is where sparks end up out of sight. Wind, weather and total fire ban rules. Smoke detectors or sprinklers isolated only with approval, and back on at close-out. Ventilation and PPE right for the fumes. Any "no" means the permit doesn't get issued yet.
Issue and accept. The supervisor signs that the checks are done. The person doing the work signs that they've read the conditions. Two signatures, so both people own it.
Close-out. Once the work stops, the fire watch stays on and checks the area again, including the other side of any wall or floor. Smouldering insulation can take a while to show. The regulators don't set a fixed time, and SafeWork NSW asks for a post-work check for smouldering material. The template suggests at least 30 minutes, a common site minimum. Your head contractor, insurer or AS 1674.1 may ask for longer.
Total fire ban days
On a total fire ban day, hot work in the open is either banned or allowed only under conditions or an exemption set by your state's fire service. In NSW, for example, the RFS says welding, grinding and gas cutting are not to be done in the open without an exemption. The rules differ by state, so check your state fire service's rules before issuing a permit on a fire ban day.
Hot work permit example: one filled-in permit
This is one permit on a two-storey house renovation, filled in the way the template asks. The job and the names are made up.
Date: Thursday 12 November. Time: 9:00 am to 12:00 pm. Location: Ground floor laundry, east wall.
Work: Brazing copper water pipes. Done by: Mia Tran, Coastline Plumbing. Fire watch: Sam Nguyen.
Precautions: Wall cavity has pine framing and foil sarking, so a fire blanket goes inside the cavity behind each joint. Cardboard and offcuts cleared from the laundry. 2.5 kg dry chemical extinguisher with Sam. Checked the room behind the wall and the subfloor. Not a fire ban day. All ten done.
Issued by: Dan Pearce, 8:50 am. Accepted by: Mia Tran, 8:55 am.
Close-out: Brazing finished 11:20 am. Sam stayed until 12:05 pm, checked the cavity, the room behind and the subfloor by hand. Closed out by Dan, 12:10 pm.
The fire blanket behind the joint is the line that matters. Brazing inside a framed wall puts the flame centimetres from pine and foil.
What people get wrong
A permit book in the ute. A pad of permits nobody fills in until after the work is a record of nothing. The permit is signed before the first spark.
No real fire watch. "Fire watch: Mia" when Mia is doing the brazing doesn't count. It's a second person.
Leaving at knock-off. Hot work late in the day is where the close-out gets skipped. Schedule hot work so the fire watch can finish before everyone leaves.
Doing it without the permit book
In Foreman's forms, build the permit once with the same sections: a single select for the type of work, a to-dos checklist for the precautions, a text field for the fire watch, and signature fields for the supervisor and the person doing the work. Turn on the date lock and the permit can't be backdated.
A sent form can't be edited, so build the close-out as a second short form: work finished, when the fire watch ended, areas checked, and a signature. The fire watch sends it before they leave.
For the step-by-step, see how to build a form template. Already have a permit on paper or as a PDF? Connect Claude or ChatGPT to Foreman, give it your PDF, and ask it to build the form for you.
Every permit is saved against the job, so the hot work permits, the site diary and the SWMS for the same day sit in one place.
Related
The daily pre-start checklist asks whether permits are in place before work starts. For high risk work, see what a SWMS is and when you need one. The hazard report form is how the crew flag anything that could start a fire before it does.
Sources
Every source used on this page traces to one of these. We recheck them when we update the page.
- Hot work safety alert. SafeWork NSW, checked 23 November 2026.
- Total fire ban rules. NSW Rural Fire Service, checked 23 November 2026.
- Model Work Health and Safety Regulations (1 July 2024). Safe Work Australia, checked 23 November 2026.