Free hazard report form template for construction sites
Who found it and where, the hazard and a photo, what was done straight away, how bad it could be, who fixes it by when, and a close-out. With a filled-in example.
Hazard report form
PDF, 1 page, A4 · Free · No email required
Want the crew to actually report hazards? Build this form once in Foreman's forms, and anyone on site with a login reports one on their phone with a photo, dated and against the job. Start free on your first job

A hazard report form is how anyone on site flags something that could hurt someone, before it does. This one-page form covers who found it and where, what the hazard is, what they did straight away, how bad it could be, and who fixes it by when. The last section closes it out, so you can show it was dealt with.
Free, no email required.
What goes on a hazard report
Who found it, and where. Name, company, date, time, and a location precise enough that someone else can walk straight to it. "Level 1" isn't enough. "Level 1, north stair void, next to the temporary handrail" is.
The hazard. Tick a type, then describe what it is and how it could hurt someone. The types are there to speed up the crew, not to make them think. The list covers the usual ones on a building site: falls, falling objects, electrical, plant and housekeeping.
What they did straight away. Barricaded it, tagged it out, stopped work, told the people nearby. A hazard report isn't a substitute for making it safe. It's the record that someone did.
How bad it could be. Four levels, from minor first aid to could kill. Extreme or High means the work in that area stops and the supervisor hears about it now, not when they get to the paperwork. If you want a finer rating, rate it on the free risk matrix.
Fixing it. The supervisor or site manager writes what will be done, who's doing it and by when. Work down from the strongest fix: get rid of the hazard if you can, then guard it, isolate it or change how the work is done, and PPE last. If the fix changes how a high risk job is done, update the SWMS too.
Closed out. What was done, who checked it worked, and when the person who reported it was told. That last line matters more than it looks.
Hazard report example: one filled-in form
This is one report on a two-storey house frame, filled in the way the template asks. The job and the names are made up.
Reported by: Josh Reilly, carpenter. Tuesday 10 November, 7:40 am. Where: Level 1, north stair void, beside the temporary handrail.
Hazard: Fall or open edge. The plywood cover over the stair void has been moved to get a stair stringer in, and nobody put it back. Anyone walking backwards with a wall frame could step straight into a 2.7 m drop.
Done straight away: Put the cover back and screwed it down. Told Sam and the plumbers on that level.
How bad: Extreme.
Fixing it: Dan Pearce, site supervisor. Swap the loose cover for a fixed handrail around the void today, and add "covers stay fixed" to tomorrow's pre-start. Dan, by 3 pm.
Closed out: Handrail fitted 1:30 pm, checked by Dan. Josh told at smoko.
The cover was fixed in two minutes. The report is what made sure it didn't happen again on Thursday.
Hazard report, incident report, or both?
A hazard is something that could hurt someone. An incident is when something has happened: an injury, a near miss, damage. If you're not sure, ask whether anyone or anything was actually hit. If yes, it's an incident: use the incident report form. Some incidents must be reported to your state's regulator straight away. See which construction incidents are notifiable. Plenty of builders use one form for both. Keeping them separate makes it easier for the crew to report a hazard without it feeling like they're dobbing someone in for an accident.
What people get wrong
Making it hard to report. If reporting a hazard means finding a clipboard in the site shed, it won't happen. The best hazard report is the one a crew member can send from where they're standing, with a photo.
Never closing the loop. The crew watch what happens to their reports. If nothing comes back, they stop reporting. Tell the person who found it when it's fixed.
Filing it and forgetting it. The same hazard turning up three times is a pattern. Read back over the reports before each toolbox talk, and use the repeat offenders as the topic.
Doing it without the clipboard
In Foreman's forms, build the crew's part as one form: a single select for the hazard type and the rating, text fields for the description and what was done, a photo field, and a project field so every report lands against the right job. Make it available to all site crew, since the whole point is that anyone can report. Turn on the date lock and the report can't be backdated.
A sent form can't be edited, so build the fix and close-out as a second short form for your site managers: which hazard, what was done, when, and a signature. Subbies need a Foreman login to report through the app. The paper form works for everyone.
For the step-by-step, see how to build a form template. Already have a hazard report on paper or as a PDF? Connect Claude or ChatGPT to Foreman, give it your PDF, and ask it to build the form for you.
Admins see every report across your jobs, and site managers see the reports for their sites, filtered by form, project and date. The person who reported it can look back at what they sent.
Related
The daily pre-start checklist is where the crew hear about this morning's hazards. The free risk matrix rates a hazard by likelihood and consequence. For high risk work, see what a SWMS is and when you need one. If something nearly happened, see what to do after a near miss.
Sources
Every source used on this page traces to one of these. We recheck them when we update the page.
- Model Code of Practice: How to manage work health and safety risks. Safe Work Australia, checked 23 November 2026.
- Model Work Health and Safety Regulations (1 July 2024). Safe Work Australia, checked 23 November 2026.