Free test and tag register template for construction sites
Each test visit with the tester's details, every lead, tool and RCD with its result and retest date, and the RCD push-button tests between visits. With the testing intervals and a filled-in example.
Test and tag register
PDF, 1 page, A4 landscape and Excel · Free · No email required
Build this register once in Foreman's forms, and each test visit and RCD check is logged on a phone with a photo of the tester's report, saved against the job. Start free on your first job

A test and tag register is the record of every lead, power tool, portable board and RCD tested on your site: who tested it, when, whether it passed, and when it's due again. This one-page register covers each test visit, plus the RCD push-button checks your crew do between visits.
Free, no email required.
Do you need a test and tag register on a building site?
Yes, in practice. Under the model WHS Regulations, a business doing construction work must comply with AS/NZS 3012, the Australian Standard for electrical installations on construction and demolition sites (reg 163). Separately, electrical equipment used where it's likely to be damaged, which describes most building sites, must be regularly inspected and tested by a competent person (reg 150). RCDs must be tested regularly too (reg 165).
The record is spelled out. For each item, reg 150 says to keep the name of the person who tested it, the date, the outcome and the date of the next test. You keep it until the item is next tested or permanently removed. The regulation says the record can be the tag itself. A register is what lets you find it when a head contractor or an inspector asks, without walking the site reading tags.
Victoria is different. It isn't under the model WHS laws. WorkSafe Victoria's industry standard for electrical installations on construction sites applies there, and it's stricter on RCDs. See the intervals below.
Queensland has its own rule too. Under the Electrical Safety Regulation 2026 (s 140), construction electrical equipment must comply with AS/NZS 3012, and the tag must show the retest date and the tester's name or licence number.
How often things need testing
These are the intervals regulators publish from AS/NZS 3012. Check them against the current standard or your state regulator before you rely on them.
| What | Test | How often |
|---|---|---|
| Leads, power tools, portable boards | Inspect and test, tag | Every 3 months |
| Portable RCDs | Push-button test | Every day, after plugging in |
| Portable RCDs | Trip-time test | Every 3 months (Victoria: monthly) |
| Fixed RCDs (site switchboard) | Push-button test | Every month |
| Fixed RCDs (site switchboard) | Trip-time test | Every 12 months (Victoria: monthly, up to 3 months if justified) |
| Site sheds and other transportable structures | Inspect and test | Every 6 months |
Under reg 150, brand-new equipment doesn't need an electrical test before first use. On site, still give it a visual check, a tag with its retest date, and a line on the register.
What goes on the register
The visit. Site, tester name and licence or certificate number, the date, and when the next visit is due. Your sparky or test and tag contractor will usually hand you their own report. Attach it, and keep this page as the site's summary.
Each item. Tag number, what it is, make or serial, whose it is, the visual and electrical result, the RCD trip time if it's an RCD, pass or fail, what happened to a failure, and the retest date. "Whose it is" matters on a building site, where half the leads belong to the subbies.
RCD push-button tests. The daily and monthly tests the crew do between visits. They take seconds, and a no means the RCD comes out of service today.
Test and tag example: one filled-in visit
This is one visit on a two-storey house build, filled in the way the template asks. The job and the names are made up.
Date: Monday 2 November. Tester: Coastline Electrical, licence number recorded. Next visit due: early February.
Tested: 23 items. 21 passed, including the site switchboard RCDs and both portable RCDs.
Failed: Tag 0417, 15 m extension lead, Coastline Plumbing. Outer sheath split near the plug. Tagged out and cut off by the tester. Tag 0422, angle grinder, Reilly Carpentry. Failed the electrical test. Tagged out, Josh taking it in for repair.
RCD push-button tests: Daily on the portable RCDs, monthly on the board. All tripped, logged by Dan.
Two failures is why you test. The register is how you show both were pulled, not left in the back of a ute.
What people get wrong
Testing once at the start of the job. On a build that runs six months, the gear tested in week one is out of date by week 14. Book the next visit before the tester leaves.
Forgetting the subbies' gear. A faulty lead on your site can hurt your crew, whoever owns it. Have your tester do theirs too, or sight their current tags and put them on the register.
Skipping the push-button test. It's the test that catches a dead RCD between visits, and it's the one that never gets written down.
Doing it without the clipboard
In Foreman's forms, build the register once: a single select for "test visit" or "RCD push-button test", text fields for the tester and their licence number, the items passed and the failed items with their tags, a photo field for the tester's report, a date for the next test, and a signature. Lock the visit date to today and an entry can't be backdated. Leave the next-test date unlocked. For a line per item, keep the Excel register alongside: the form records each visit and what failed.
For the step-by-step, see how to build a form template. Already have a register as a spreadsheet or a PDF? Connect Claude or ChatGPT to Foreman, give it the file, and ask it to build the form for you.
Every entry is saved against the job, so when someone asks for the electrical test records, they're filtered by form and project in one list.
Related
The daily pre-start checklist checks that plant and tool tags are in date each morning. Use the hazard report form for a damaged lead found between visits. For high risk work, see what a SWMS is and when you need one.
Sources
Every source used on this page traces to one of these. We recheck them when we update the page.
- Model Work Health and Safety Regulations (1 July 2024). Safe Work Australia, checked 23 November 2026.
- Inspection and testing of electrical equipment. SafeWork SA, checked 23 November 2026.
- Electrical Safety Regulation 2026. Queensland Government, checked 23 November 2026.
- Industry standard: Electrical installations on construction sites. WorkSafe Victoria, checked 23 November 2026.