Free scaffold inspection checklist for builders
The scaffold's details, the scaffolder's handover, 14 checks including mobile scaffolds, the result and both signatures. With when an inspection is required and a filled-in example.
Scaffold inspection checklist
PDF, 1 page, A4 · Free · No email required
Inspecting scaffolds on several jobs? Build this checklist once in Foreman's forms, and your site manager ticks the checks, photographs the handover certificate and signs on their phone. Start free on your first job

A scaffold inspection checklist is the record that a competent person looked over a scaffold, found it complete and safe, and signed for it. This one-page version covers the scaffold's details, the scaffolder's handover, 14 checks, the result, and the inspector's and builder's signatures. Use it at handover and for every re-inspection after that.
Free, no email required.
When a scaffold must be inspected
Under the model WHS Regulations (reg 225), the person who manages or controls a scaffold must make sure it isn't used until a competent person has inspected it and confirmed in writing that it's complete. After that, a competent person must inspect the scaffold and what it stands on:
- before it's used again after an incident that could affect its stability, such as a vehicle hitting it or a big storm
- before it's used again after repairs
- at least every 30 days.
The rule covers any scaffold someone or something could fall more than 4 metres from, plus suspended, cantilevered, spur and hung scaffolds of any height. If an inspection finds a problem, it's fixed and inspected again before anyone goes back up. While a scaffold is incomplete or unattended, you also have to stop people getting onto it, usually with danger tags and barriers.
Victoria isn't under the model WHS laws and has its own scaffold rules, so check WorkSafe Victoria's requirements there. For a scaffold under 4 m that isn't one of those types, a regular inspection is still the simplest way to show you managed the risk of falls.
What goes on the checklist
The scaffold. Location or ID, height, type (modular, tube and coupler, mobile, trestle), duty rating, and why it's being inspected: handover, the 30-day check, bad weather, an incident or alterations.
The scaffolder's handover. Their company and licence number, and whether you sighted their handover certificate. Scaffolding work where someone or something could fall more than 4 metres needs a high risk work licence. Keep a photo of the certificate with this sheet.
The checks. Clear of powerlines, sole boards and base plates, ties and bracing as designed, guardrails, mid-rails and toeboards, fully planked decks, the gap to the building, safe access, load within the duty rating, sheeting secure, and the scaff tag filled in. Mobile scaffolds get three more: castors locked, plan bracing and guardrails.
The result. Safe to use, or unsafe with access stopped. Write what was wrong and what you did about it.
Sign-off. The inspector's name, competency and signature, and the builder or site manager's.
Scaffold inspection example: one filled-in check
This is one 30-day inspection on a two-storey house, filled in the way the template asks. The job and the names are made up.
Date: Tuesday 17 November. Scaffold: north and east elevations, modular, medium duty, 7.2 m to the top working deck. Reason: 30-day inspection. Scaffolder: Coastline Scaffolding, licence number recorded. Handover certificate from 20 October sighted and photographed.
Checks: 10 OK, one not OK, three N/A (not a mobile scaffold). Not OK: a guardrail and mid-rail missing on the east side top lift, taken off by the roofers yesterday to land sheets and not put back.
Result: Unsafe, access stopped to the east top lift. Danger tag on the ladder hatch. Scaffolder called, rails refitted 1:15 pm, re-inspected and signed off 1:40 pm.
Inspector: Dan Pearce, site supervisor, scaffold inspection training. Builder: signed.
The rails were off for a day. The 30-day check found it, but the roofers' pre-start should have found it first.
What people get wrong
Treating the scaff tag as the inspection. The tag shows the last inspection. The written record shows what was checked, by whom, and what was wrong.
Letting trades alter it. Rails come off to land materials and don't go back on. Only a licensed scaffolder should alter a scaffold over 4 m, and the model regulations require an inspection before it's used again after repairs. Treat any alteration the same way.
Missing the 30 days on a long job. On a build that runs five months, that's at least five inspections. Book the next one when you sign off this one.
Doing it without the clipboard
In Foreman's safety forms, build the checklist once: single selects for the reason, type and duty rating, text fields for the location and the scaffolder's licence, a photo field for the handover certificate, a to-dos checklist for the checks, a single select for the result, and signature fields for the inspector and the builder. Make it available to site managers and admins only, so the inspection stays with the people who are meant to do it. Turn on the date lock and an inspection can't be backdated. If an inspection fails, the re-inspection after the fix is a new form, so the record shows both.
For the step-by-step, see how to build a form template. Already have a scaffold checklist on paper or as a PDF? Connect Claude or ChatGPT to Foreman, give it the file, and ask it to build the form for you.
Every inspection is saved against the job, so the 30-day trail for each job is one filtered list.
Related
The site safety inspection checklist checks that the scaff tag is current on every weekly walk. The daily pre-start checklist is where the crew hear that a lift is closed. For high risk work, see what a SWMS is and when you need one.