How long do you need to keep safety records?
The retention periods the WHS laws actually set, the site records that have none, why 5 years is the safe benchmark, and where Victoria differs.
Most site safety records have no set retention period at all. The ones that do: notifiable incident records for at least 5 years, and a SWMS until the high risk work is finished, or at least 2 years after a notifiable incident connected with it. For everything else, keep it at least 5 years after the job, which covers the incident record period and the usual window for a prosecution.
Throwing the site folder in the skip at handover is the common mistake. The question about a job usually turns up long after the job is finished, and the record you threw out is the one you needed.
The retention periods set in law
These come from the model WHS Act and Regulations, which every state and territory except Victoria has adopted. Where Victoria differs is in the state table below.
| Record | How long to keep it | Where it comes from |
|---|---|---|
| Notifiable incident record | At least 5 years from the day you notified the regulator | WHS Act s 38(7) |
| SWMS | Until the high risk construction work is finished. At least 2 years after any notifiable incident connected with it | WHS Regulations reg 303 |
| WHS management plan | Until the construction project is finished. At least 2 years after any notifiable incident connected with it | reg 313 |
| Underground services information | Until the excavation is finished. At least 2 years after any notifiable incident connected with it | reg 304 |
| Electrical test record | Until the item is next tested, or removed from site or thrown out | reg 150 |
| Records for registered plant, such as a tower crane | For as long as you use the plant, or until you hand over control | reg 237 |
| Asbestos training record | While the worker does the work, and 5 years after they stop working for you | reg 445 |
| Confined space training record | 2 years | reg 76 |
| Health monitoring reports, such as for lead | At least 30 years, kept confidential | reg 378 and 418 |
| Asbestos health monitoring reports | At least 40 years, kept confidential | reg 444 |
Two more rules sit alongside these. A copy of the SWMS has to be readily available to the workers doing the job for as long as it must be kept. And a hazardous chemicals register has no end date, because it has to stay up to date for as long as the chemicals are on site (reg 346).
The records with no set period
No WHS law sets a period for these. Most of a small builder's paperwork is in this group:
- site induction records
- toolbox talk records
- daily pre-starts
- hazard reports and near miss reports
- site inspections, plant checks and ladder checks
- scaffold handover certificates and inspection records
- first aid kit checks and first aid treatment records
- the site diary
No period doesn't mean no value. These are the records you'll be asked for when something goes wrong, and they only help if you still have them.
Why 5 years is the safe benchmark
A prosecution under the WHS Act can be brought up to 2 years after the offence first comes to the regulator's notice, or 1 year after a coronial report or inquest, whichever is later (s 232). An offence can come to the regulator's notice long after the job, so the clock can start late. A Category 1 offence can be brought later still if new evidence turns up, and Victoria has its own rule.
Five years lines up with the notifiable incident record, and it covers the safety law windows. Treat it as a benchmark. If a job had a serious incident, a dispute, or a worker who may make a claim later, keep everything from it for longer.
Some records outlast safety law. Timesheets and pay records fall under Fair Work record-keeping rules, which set their own period. Your contract may require records for the defects period or longer. Check both before you throw anything out.
State by state
| State or territory | What's different |
|---|---|
| Victoria | Own law. Keep the written notifiable incident record at least 5 years. Keep the SWMS for the duration of the high risk work. Victoria has no 2-year rule after an incident for the SWMS. |
| NSW | Model rules. Its WHS Regulation 2025 calls them sections, not clauses, with the same construction numbers. |
| Queensland | Model rules. |
| South Australia | Model rules. |
| Western Australia | Model rules since 31 March 2022. |
| Tasmania | Model rules, under the WHS Regulations 2022. |
| ACT | Model rules, plus a silica training record (below). |
| Northern Territory | Model rules. |
Every state and territory other than Victoria adopted the model laws, but each has its own instrument, and the numbering is not always the same. Check your own regulation before you quote a number to anyone.
The ACT added processing crystalline silica with power tools to its high risk work list, and with it a 5-year record of silica training (s 418D). If you cut or grind stone, brick or concrete in the ACT, that record applies to you.
Keep it findable, not just kept
A box of paper in a shed is kept. It isn't findable. The test is whether you can pull out one worker's induction from a job three years ago in a couple of minutes.
- One place per job. Not a folder in the shed, a WhatsApp group and someone's email.
- Dated on the day. A record written at the time carries weight a reconstruction doesn't.
- Kept after handover. Archive the job, don't bin it.
- Electronic is fine for a SWMS. Safe Work Australia and WorkSafe Victoria both say a SWMS can be kept electronically.
How Foreman keeps them
In Foreman, every site induction lands in your induction register against that job, with the person's signature, the documents they were shown, and the time they signed. Every form your crew fill in, from the pre-start to the hazard report, is saved with who sent it, when, and which job it belongs to. You build the forms yourself in a few minutes (how to build a form template), and a new account starts with one sample. Foreman's site diary records when each entry was submitted, separately from the day it covers.
When the job's done, archive it. Nothing is deleted: diaries, inductions and forms are all kept, and an Admin can open them whenever they're asked for. Each induction downloads as a signed PDF, each project downloads as a ZIP of CSVs, and the diary exports as a CSV or a PDF with photos (export a site diary). That's your copy for the filing cabinet or the head contractor.
Related
What safety forms a builder needs covers which records to make in the first place. Notifiable incidents on a building site covers the 5-year incident record, and is a site diary legally required covers the diary.
This page explains general obligations and is not legal advice. For a specific situation, check with your state regulator or get advice.
Sources
Every source used on this page traces to one of these. We recheck them when we update the page.
- Model Work Health and Safety Regulations (1 July 2024), regs 76, 150, 237, 303, 304, 313, 346, 378, 418, 444, 445. Safe Work Australia, checked 23 November 2026.
- Model Work Health and Safety Bill as at 5 December 2025, ss 38(7) and 232. Safe Work Australia, checked 23 November 2026.
- Work Health and Safety Act 2011 (Qld), ss 38 and 232. Queensland Legislation, checked 10 November 2026.
- Notifiable incidents under the Occupational Health and Safety Act 2004. WorkSafe Victoria, checked 23 November 2026.
- Safe Work Method Statements (SWMS). WorkSafe Victoria, checked 26 October 2026.
- Safe work method statement for high risk construction work: information sheet. Safe Work Australia, checked 26 October 2026.
- Work Health and Safety Regulation 2025 (NSW). NSW Legislation, checked 12 October 2026.
- Work Health and Safety Regulation 2011 (ACT), ss 291 and 418D. ACT Legislation Register, checked 15 October 2026.
- Work Health and Safety Regulations 2022 (Tas). Tasmanian Legislation, checked 15 October 2026.