Site diary vs daily report: one record, two names

Builders keep a site diary. Head contractors ask subbies for a daily report. Keep one record of the day and send it under whichever name they use.

Published 6 min read

A site diary and a daily report are the same record: a dated account of one day on one job, covering who was on site and for how long, what got done, what arrived and what held the work up. Builders usually call it a site diary and head contractors usually ask subbies for a daily report, so you can keep one record and hand it over under whichever name the person asking uses.

The names change with who is asking and the day underneath stays the same. You'll also hear daily log, construction diary, site report and daily construction report, and on a small job they all point at the same page.

Why there are two names

The split mostly follows which side of the subcontract you're on.

When you run your own job, the diary is yours. You keep it to back up a variation or a rain delay, and what goes in it is up to you. Most builders call that a site diary.

When you work as a subbie on someone else's job, the head contractor wants a record from you too. They are tracking labour and progress across every trade on site, and "daily report" is the word their site team tends to use. Your subcontract may say what goes in it and when it's due. That's the place to check, because terms vary between head contractors.

Plenty of builders sit on both sides in the same month. You run a renovation of your own on Monday and you're framing for a bigger builder on Tuesday. That's usually when the question comes up, because it feels like two jobs' worth of paperwork.

What each one usually covers

Here is how the two compare on a typical small job. The head contractor column is general. Their own form, if they have one, is what counts.

What's recordedBuilder's site diaryDaily report for a head contractor
Date and jobYesYes
Who was on site and their hoursYes, your crew and anyone else on the jobUsually your crew numbers and hours
Work completedYes, in your own wordsYes, often by area or stage
WeatherYes, especially anything that stopped workOften
Deliveries and plantYesSometimes
Delays and their causeYes, the most important lineYes
Instructions and variations given on siteYesSometimes, or on a separate form
Safety matters and near missesYesOften, or on a separate form
PhotosYes, before work is covered upSometimes asked for
Who it's forYou, laterThe head contractor, today

Almost every row overlaps. The real differences are who reads it and when they want it.

Where they genuinely differ

A diary is written for you, months from now, when a client disputes a variation or you need to show why the slab pour moved. It can be as full as you like. A daily report is something you send. Someone else reads it, usually soon after, and they may want it in their format by a set time.

That leads to the mistake worth avoiding: writing the day twice. A tired supervisor fills in the head contractor's form at the gate, then writes a shorter diary entry at home, or skips the diary because the form felt like enough. Now there are two accounts of the same day, written at different times, and they will disagree on something, usually the hours or who gave the instruction. If that day is ever argued over, the gap between them is the first thing someone reads.

Keep one record and send copies of it.

How one record covers both

  1. Write it on site, on the day. Before you leave the gate. An entry written that afternoon has the detail that a Sunday-night version from memory and a camera roll won't.
  2. Put the head contractor's items in it. If their form asks for crew numbers, areas worked and delays, write those into the entry as a matter of habit. Then the diary already holds everything they want.
  3. Take the photos with the entry. Shoot work that's about to be covered up and anything that came short, and attach them to that day.
  4. Send a copy, filtered to their job. When the head contractor asks, give them that job's entries for the dates they want, as a PDF. Your other jobs stay out of it.
  5. If they insist on their own form, copy across. Fill it in from the diary entry rather than from memory, so both say the same thing.

How to keep a site diary that holds up later has a worked example of a bad day on site and the order to write it in.

Doing it in Foreman

Foreman's site diary keeps one entry per person, per job, per day: the date, the hours, a note on what got done and photos taken in the app. Each entry records when it was submitted, separately from the date it covers, and with location turned on it shows whether it was written on site or off site. If someone edits an entry later, its history shows who changed what.

When a head contractor asks for a daily report, open Site diaries, filter to their project and the date range they want, and download the PDF. It opens with your business logo (or name), the project and the date range, and a summary of entries, hours, people and photos. Then comes every entry grouped by day with who, their check-in and check-out times or "Entered by hand", the hours, the full note and the photos two to a row. It's made to attach to an email for someone who isn't on Foreman. A CSV of the same view is there too if they want the hours in a spreadsheet. Admins can export any project and Site Managers can export the projects they manage. Crew can't export.

One limit to know. Foreman has no separate fields for weather, deliveries or delays, and it won't fill in a head contractor's own template for you. Those items go in the entry's note, in plain words, and the PDF is what you send. If you need to back up a rain day, a weather record for that address can sit next to the diary entry. A very long date range with a lot of photos may also need splitting, because each PDF holds up to 300 entries and 120 photos.

Your first project is free forever, with every feature and unlimited users on it, and no card. After that it's $29 + GST a month for each person with a login, or $23.20 + GST a month billed yearly.

Which name should you use

Use the name the person asking uses. If the head contractor wants a daily report, send them your diary entries for their job and call it a daily report. If a client or an adjudicator asks for your site diary, it's the same file.

In your own business, pick one name and stick to it, so nobody on your crew thinks there are two things to fill in. If your crew already say site diary, keep it.

Whether you're legally required to keep one is a separate question, with a different answer for law and for contracts: is a site diary legally required in Australia covers it. If you're comparing apps, site diary apps for Australian builders, compared sets them side by side.

Frequently asked questions

Is a site diary the same as a daily report?
Yes, in practice. Both are a dated record of one day on one job: who was on site and for how long, what got done, deliveries, and anything that held the work up. Builders usually call it a site diary. Head contractors usually ask subbies for a daily report.
What should a construction daily report include?
The date and job, who was on site and their hours, the work completed, weather, deliveries and plant, delays and their cause, instructions given on site, safety matters, and photos of work before it is covered up. If the head contractor has their own form, it decides what they want.
Can I send my site diary to a head contractor as my daily report?
Usually, yes, if it holds what they ask for. Filter your diary to their job and the dates they want and send it as a PDF. If they insist on their own form, fill it in from your diary entry so both records say the same thing.
Should I keep a separate diary and daily report?
No. Two accounts of the same day, written at different times, will disagree on something, and that gap is what gets read out if the day is ever disputed. Keep one record written on the day and send copies of it.

Keep your sites in order

One record of the day, for you and the head contractor.

Crew log the day on their phone, and you send a PDF of any job and date range when someone asks. Free forever on your first project, with every feature and unlimited users on it.

Foreman is a member of Master Builders Queensland.